2026 Capital Budget Jan 01-Oct 31

Projects2026 Budget2026 Total Allocation2026 Actuals From GLNotes
Fire
Tanker Replacement550,000750,000180,335The replacement vehicle has been ordered, with an anticipated delivery timeline of approximately 18 months. A 20% deposit has been paid, with the remaining balance payable as the purchase progresses.
CAD Upgrade18,000137,901-The upgrade has been ordered. Bell has advised of an approximately 120-day delivery/implementation lead time from July 2026, and the project is awaiting completion by the service provider.
Fire Hall Building Expansion128,400128,400-The project is currently on hold pending the outcome of ongoing negotiations. Further work will proceed once negotiations have been concluded
Personal Protective Equipment35,00035,000-The project is planned to proceed, with the required equipment expected to be ordered before the end of 2026.
SCBA Washer51,00051,000-The equipment has been ordered, with an anticipated delivery timeframe of approximately 16 weeks from August 2026.
Total782,4001,102,301180,335
Police
Annual Vehicle Replacement100,000100,000106,403The project has been successfully completed.
NG 911 System25,00025,000-The transfer is scheduled to be completed as part of the year-end process.
CAD Mapping73,67573,67537,486Mapping information has been received from the surrounding municipalities for the area extending five kilometres beyond the Town's boundaries. This information will be incorporated into the Town's mapping system.
Vehicle Tablets24,00024,0006,411Lightly used tablets were purchased from other services, providing the required equipment while making effective use of available project funding.
New Water Tower Upgrade-Emergency Antenna50,00050,000-Equipment located on the former water tower is scheduled to be removed in 2026 as part of the decommissioning process.
Police Station Roof Repair20,00020,000-The project has not started yet
Mobile interview kit70,00070,000-No work has been completed on this project yet.
Total362,675362,675150,300
Parks

Lower Reach Parking Lot - Lower Reach Park-724,60490,548Tender results will be presented to Council for consideration as part of the 2027 budget process. As directed by Council, the funding was redirected to capital infrastructure. A new finger dock has been purchased for Lower Reach Park, as has an accessible kayak launch (installation Nov); sidewalk installed off Park Ave to bridge, and the full project budget is expected to be spent in 2026.
Waterfront Trail Plan60,00085,00025,026As directed by Council, the funding was redirected to capital infrastructure. A new finger dock has been purchased for Lower Reach Park, and the full project budget is expected to be spent in 2026.
Zero Turn Lawnmowers (2)50,00050,00049,877Project Complete.
Christmas Lights30,00030,00027,902Project Complete
Bellamy Farms Playground - Bellamy Farms (new) Furniture250,000250,00050,100Project Complete.
Urban Forest Expansion30,00030,00023,178Project Complete.
Water Connection Centennial Park15,00015,000-Project Complete.
Outdoor Furniture Revitalization75,00075,00074,649Project Complete
Lower Reach Play Structure195,000195,000-Project now complete. Awaiting Invoices.
Abbott Lombard Gateway Feature55,00055,0004,291The project is underway, with the design expected to be presented to Council in September 2026.
Cat Trailhead Materials-5,0913,603Project Complete.
Picnic Tables15,00015,0001,361Project complete; additional picnic tables and accessories have been purchased; awaiting delivery and invoicing.
Total775,0001,529,695352,800
Facilities
HHM Painting- Interior/Exterior - HHM-70,00079,488Project complete
Town Hall Complex Roof, Returned Eaves and Cupola Replacement-225,000195,407Project Complete.
Replacement Air Handling Unit - Memorial Community Centre-45,0009,750The project is underway and is expected to be completed by December 2026.
Public Works Operations Centre Design Study-36,97725,348The design work is complete, including a Class C cost estimate. The project has now been transferred to Public Works for the next phase.
MCC Barrel Roof Repair 01-21-241-010-612325,00050,00044,043Project complete
Cemetery Building Upgrades45,00045,00033,901The project is underway and is expected to be completed by December 2026.
Civilian Building at the Ball Field Upgrades45,00045,0002,491The project is underway and is expected to be completed by December 2026.
HHM Furnace Replacement (2)35,00035,000-The project is underway and is expected to be completed by December 2026.

HHM Exterior Upgrades140,000140,000439The project is underway and is expected to be completed by December 2026.
Regional Recreation Complex Phase 2250,000250,0003,750The project is underway, with some work and funding likely to carry forward into 2027.
Station Theatre Upgrades90,00090,0001,791The project is underway and is expected to be completed by December 2026.
Visitor Centre Upgrades85,00085,000-The project is underway and is expected to be completed by December 2026.
Tables and chairs - Community Centre Hall/Youth Arena Hall15,00015,00010,000Project Complete.
Total730,0001,137,785409,577
Library
Back Door Replacement15,00015,0009,637Project complete. Waiting on the final invoice under $1,000.
Total15,00015,00017,693
Water
Trunk Main for Water Tower - Phase 15,000,00014,977,522128,474Phase 1 of the larger project began the week of August 10, 2026, and is expected to be completed in December 2026.
Water Meter Replacement - Committed in 2025825,000825,000769,301The project is underway and is expected to be completed by the end of 2026.
SCADA-20,910-The project is ongoing and nearing completion.
Water Hydraulic Modelling-50,00035,047A preliminary report has been presented. The next phase will consider future needs, including potential expansion and development within the Town's boundaries.
Dissolved Air Flotation (DAF) maintenance-9,3542,229Nearing Completion
Replacement of last two sections of High Lift piping-70,00057,316The first phase of the piping work is complete, including work on the raw water line. One remaining section requires emergency
New SCBA (x2) (Budget reflective of 2)-17,475-The equipment is onsite and now in service
Process Control Narrative and Operational Plan-15,0005,133A preliminary report has been received and is currently being reviewed by staff.
Granulated Activated Carbon (GAC) filter top-up to be removed20,000--Materials have been purchased and are onsite, with installation planned for fall 2026.
Hydro guards - McDonald St. and Robina Ave.24,00024,00014,484The tower cameras have been installed and are now in service. Fencing has been ordered and is expected to be installed in 2026.
Water Tower Security Cameras and Fence28,70028,7003,611Fencing has been completed and is onsite. The communications building is onsite, with electrical and conduit work complete and ready for installation of the communications
Water Tower Generator and Communications Building100,000100,00081,354New pumps and hoses have been ordered for Utilities to replace aging and damaged equipment.

Pumps and Fittings15,00015,00013,804Project is complete
Utilities Trailer25,00025,00022,144Project is complete
Valve Nut RX Kit16,50016,500-The sections of piping to be replaced have been quoted and are now being fabricated.
Stainless Pipe Replacement75,00075,000-The project is approximately 95% complete. All but one hatch have been serviced. The remaining hatch is being modified to improve winter operation and will then be serviced. Final invoices
Reservoir + BET Hatch Replacement40,00040,00036,956The equipment has been purchased and installed and is now in service.
Radio Systems Update20,00020,00016,433The inspection is complete and some maintenance is required on the chlorine injection system. A quote is being obtained for the required repairs.
Intake/Diversion Chamber RWW Dive/ROV15,00015,0005,699Ordered and onsite.
Chlorine System Parts30,00030,00028,971Project is near completion
Backup Central UPS System65,00065,000-The project is complete, with the equipment installed and now in service.
WTP Alarm Panel Upgrade for Dialer10,00010,00012,836Project is complete
Highlift Pump Rebuild20,07720,07720,077This project was added to the capital budget later in the year and approved by Council.
WTP Replacement Air Conditioning Unit45,48745,487-The unit has been ordered and is awaiting delivery.
Decommissioning of Old Water Tower400,000400,000-The contract has been signed, and the work is expected to be completed in the spring of 2027.
Total6,774,76417,551,6401,362,407
Wastewater
Primary/Secondary Gates-253,760-Project is ongoing.
Supervisory Control and Data Acquisition (SCADA)-39,82419,466The equipment has been installed and is now in service. The project is complete.
Pelletizer; Solid Handling Eng. Study-105,21571,744Computers are being purchased. Compatibility issues have been identified with the existing alarm system, and staff are working to resolve them.
Sewer Hydraulic Capacity Study-175,000309The project is ongoing and is currently in the preliminary design stage. The design may be ready for review in the coming weeks.
Manhole Replacement at River/Elm St. Intersection-50,000-The study is underway. Data was collected throughout the summer, and the required information is now being provided to the engineers for assessment.
Pollution Prevention Control Plan-10,000-The study is underway. Data was collected throughout the summer, and the information is now being provided to the engineers for review and assessment
Process Control Narrative and Operational Plan-40,000-The project has not started yet. Work will begin once the SCADA computers have been replaced.

Tree Removal and Perimeter Fencing-8,2639,118The plant area has been cleaned up, and the area around the perimeter fencing has been cleared and restored.
M01 Raw Sewage Pump Rebuild70,00078,66873,065The equipment is complete and onsite, ready to be installed during the next scheduled pump cycle.
CIPP Sanitary Sewer210,000210,00070,952The project is ongoing at various locations throughout Town, with most of the work completed in August 2026.
Headworks Grit System Assessment100,000100,00014,444The project is currently on hold following issues identified by the Electrical Safety Authority (ESA) in the headworks area. The project scope may need to be reviewed before work proceeds.
Turbine Pump Wet End Replacement165,000165,000-Quotes are being obtained for the required equipment and parts
Tertiary Sand Filter Maintenance85,00085,00068,440Filter media replacement completed.
Raw Sludge Pump Base Replacement20,00020,00010,888New pump bases and safety guards have been fabricated and installed.
Raw Sewage Pumps250,000250,000-The project is currently on hold while electrical issues identified in the headworks area are reviewed. The findings may require changes to the project scope before work can continue.
UV System Parts25,00025,00022,908Parts have been ordered.
Pelletizer PM (contractor)30,00030,000-The required parts have been ordered, and the necessary fabrication work is complete.
Total955,0001,645,730442,257
Public Works
Beckwith/Lombard Bridge734,933734,93361,056Project is ongoing and will continue into 2027
ACMP Program Roads1,039,5261,164,283747,357Project is complete
Traffic Controllers & Intersection Improvements: Brockville and Broadview and additional sensors at Cornelia and Elmsley.200,000200,000-The project has been awarded, but work has not yet started. The contractor expects the work to be completed by the end of October 2026
Public Works Design Build10,458,52010,458,520201,777Construction began in the fall of 2026, with occupancy expected before winter 2027.
Total11,698,04611,822,8031,109,045
Planning
Building Permit Software22,50022,50023,812Implementation is underway, with the new system scheduled to go live on January 1, 2027.
Official Plan Transportation Master Plan-167,9138,118The project is ongoing, with an update to be presented to Council in the coming weeks.
Total22,500190,41331,930
Corp

Maintenance Manager Software (Public Works and Utilities)172,000172,000139,615The project is underway and is expected to be completed by the end of 2026.
Total172,000172,000140,648