2026 Capital Budget Jan 01-Oct 31
| Projects | 2026 Budget | 2026 Total Allocation | 2026 Actuals From GL | Notes |
|---|---|---|---|---|
| Fire | ||||
| Tanker Replacement | 550,000 | 750,000 | 180,335 | The replacement vehicle has been ordered, with an anticipated delivery timeline of approximately 18 months. A 20% deposit has been paid, with the remaining balance payable as the purchase progresses. |
| CAD Upgrade | 18,000 | 137,901 | - | The upgrade has been ordered. Bell has advised of an approximately 120-day delivery/implementation lead time from July 2026, and the project is awaiting completion by the service provider. |
| Fire Hall Building Expansion | 128,400 | 128,400 | - | The project is currently on hold pending the outcome of ongoing negotiations. Further work will proceed once negotiations have been concluded |
| Personal Protective Equipment | 35,000 | 35,000 | - | The project is planned to proceed, with the required equipment expected to be ordered before the end of 2026. |
| SCBA Washer | 51,000 | 51,000 | - | The equipment has been ordered, with an anticipated delivery timeframe of approximately 16 weeks from August 2026. |
| Total | 782,400 | 1,102,301 | 180,335 | |
| Police | ||||
| Annual Vehicle Replacement | 100,000 | 100,000 | 106,403 | The project has been successfully completed. |
| NG 911 System | 25,000 | 25,000 | - | The transfer is scheduled to be completed as part of the year-end process. |
| CAD Mapping | 73,675 | 73,675 | 37,486 | Mapping information has been received from the surrounding municipalities for the area extending five kilometres beyond the Town's boundaries. This information will be incorporated into the Town's mapping system. |
| Vehicle Tablets | 24,000 | 24,000 | 6,411 | Lightly used tablets were purchased from other services, providing the required equipment while making effective use of available project funding. |
| New Water Tower Upgrade-Emergency Antenna | 50,000 | 50,000 | - | Equipment located on the former water tower is scheduled to be removed in 2026 as part of the decommissioning process. |
| Police Station Roof Repair | 20,000 | 20,000 | - | The project has not started yet |
| Mobile interview kit | 70,000 | 70,000 | - | No work has been completed on this project yet. |
| Total | 362,675 | 362,675 | 150,300 | |
| Parks |
| Lower Reach Parking Lot - Lower Reach Park | - | 724,604 | 90,548 | Tender results will be presented to Council for consideration as part of the 2027 budget process. As directed by Council, the funding was redirected to capital infrastructure. A new finger dock has been purchased for Lower Reach Park, as has an accessible kayak launch (installation Nov); sidewalk installed off Park Ave to bridge, and the full project budget is expected to be spent in 2026. |
|---|---|---|---|---|
| Waterfront Trail Plan | 60,000 | 85,000 | 25,026 | As directed by Council, the funding was redirected to capital infrastructure. A new finger dock has been purchased for Lower Reach Park, and the full project budget is expected to be spent in 2026. |
| Zero Turn Lawnmowers (2) | 50,000 | 50,000 | 49,877 | Project Complete. |
| Christmas Lights | 30,000 | 30,000 | 27,902 | Project Complete |
| Bellamy Farms Playground - Bellamy Farms (new) Furniture | 250,000 | 250,000 | 50,100 | Project Complete. |
| Urban Forest Expansion | 30,000 | 30,000 | 23,178 | Project Complete. |
| Water Connection Centennial Park | 15,000 | 15,000 | - | Project Complete. |
| Outdoor Furniture Revitalization | 75,000 | 75,000 | 74,649 | Project Complete |
| Lower Reach Play Structure | 195,000 | 195,000 | - | Project now complete. Awaiting Invoices. |
| Abbott Lombard Gateway Feature | 55,000 | 55,000 | 4,291 | The project is underway, with the design expected to be presented to Council in September 2026. |
| Cat Trailhead Materials | - | 5,091 | 3,603 | Project Complete. |
| Picnic Tables | 15,000 | 15,000 | 1,361 | Project complete; additional picnic tables and accessories have been purchased; awaiting delivery and invoicing. |
| Total | 775,000 | 1,529,695 | 352,800 | |
| Facilities | ||||
| HHM Painting- Interior/Exterior - HHM | - | 70,000 | 79,488 | Project complete |
| Town Hall Complex Roof, Returned Eaves and Cupola Replacement | - | 225,000 | 195,407 | Project Complete. |
| Replacement Air Handling Unit - Memorial Community Centre | - | 45,000 | 9,750 | The project is underway and is expected to be completed by December 2026. |
| Public Works Operations Centre Design Study | - | 36,977 | 25,348 | The design work is complete, including a Class C cost estimate. The project has now been transferred to Public Works for the next phase. |
| MCC Barrel Roof Repair 01-21-241-010-6123 | 25,000 | 50,000 | 44,043 | Project complete |
| Cemetery Building Upgrades | 45,000 | 45,000 | 33,901 | The project is underway and is expected to be completed by December 2026. |
| Civilian Building at the Ball Field Upgrades | 45,000 | 45,000 | 2,491 | The project is underway and is expected to be completed by December 2026. |
| HHM Furnace Replacement (2) | 35,000 | 35,000 | - | The project is underway and is expected to be completed by December 2026. |
| HHM Exterior Upgrades | 140,000 | 140,000 | 439 | The project is underway and is expected to be completed by December 2026. |
|---|---|---|---|---|
| Regional Recreation Complex Phase 2 | 250,000 | 250,000 | 3,750 | The project is underway, with some work and funding likely to carry forward into 2027. |
| Station Theatre Upgrades | 90,000 | 90,000 | 1,791 | The project is underway and is expected to be completed by December 2026. |
| Visitor Centre Upgrades | 85,000 | 85,000 | - | The project is underway and is expected to be completed by December 2026. |
| Tables and chairs - Community Centre Hall/Youth Arena Hall | 15,000 | 15,000 | 10,000 | Project Complete. |
| Total | 730,000 | 1,137,785 | 409,577 | |
| Library | ||||
| Back Door Replacement | 15,000 | 15,000 | 9,637 | Project complete. Waiting on the final invoice under $1,000. |
| Total | 15,000 | 15,000 | 17,693 | |
| Water | ||||
| Trunk Main for Water Tower - Phase 1 | 5,000,000 | 14,977,522 | 128,474 | Phase 1 of the larger project began the week of August 10, 2026, and is expected to be completed in December 2026. |
| Water Meter Replacement - Committed in 2025 | 825,000 | 825,000 | 769,301 | The project is underway and is expected to be completed by the end of 2026. |
| SCADA | - | 20,910 | - | The project is ongoing and nearing completion. |
| Water Hydraulic Modelling | - | 50,000 | 35,047 | A preliminary report has been presented. The next phase will consider future needs, including potential expansion and development within the Town's boundaries. |
| Dissolved Air Flotation (DAF) maintenance | - | 9,354 | 2,229 | Nearing Completion |
| Replacement of last two sections of High Lift piping | - | 70,000 | 57,316 | The first phase of the piping work is complete, including work on the raw water line. One remaining section requires emergency |
| New SCBA (x2) (Budget reflective of 2) | - | 17,475 | - | The equipment is onsite and now in service |
| Process Control Narrative and Operational Plan | - | 15,000 | 5,133 | A preliminary report has been received and is currently being reviewed by staff. |
| Granulated Activated Carbon (GAC) filter top-up to be removed | 20,000 | - | - | Materials have been purchased and are onsite, with installation planned for fall 2026. |
| Hydro guards - McDonald St. and Robina Ave. | 24,000 | 24,000 | 14,484 | The tower cameras have been installed and are now in service. Fencing has been ordered and is expected to be installed in 2026. |
| Water Tower Security Cameras and Fence | 28,700 | 28,700 | 3,611 | Fencing has been completed and is onsite. The communications building is onsite, with electrical and conduit work complete and ready for installation of the communications |
| Water Tower Generator and Communications Building | 100,000 | 100,000 | 81,354 | New pumps and hoses have been ordered for Utilities to replace aging and damaged equipment. |
| Pumps and Fittings | 15,000 | 15,000 | 13,804 | Project is complete |
|---|---|---|---|---|
| Utilities Trailer | 25,000 | 25,000 | 22,144 | Project is complete |
| Valve Nut RX Kit | 16,500 | 16,500 | - | The sections of piping to be replaced have been quoted and are now being fabricated. |
| Stainless Pipe Replacement | 75,000 | 75,000 | - | The project is approximately 95% complete. All but one hatch have been serviced. The remaining hatch is being modified to improve winter operation and will then be serviced. Final invoices |
| Reservoir + BET Hatch Replacement | 40,000 | 40,000 | 36,956 | The equipment has been purchased and installed and is now in service. |
| Radio Systems Update | 20,000 | 20,000 | 16,433 | The inspection is complete and some maintenance is required on the chlorine injection system. A quote is being obtained for the required repairs. |
| Intake/Diversion Chamber RWW Dive/ROV | 15,000 | 15,000 | 5,699 | Ordered and onsite. |
| Chlorine System Parts | 30,000 | 30,000 | 28,971 | Project is near completion |
| Backup Central UPS System | 65,000 | 65,000 | - | The project is complete, with the equipment installed and now in service. |
| WTP Alarm Panel Upgrade for Dialer | 10,000 | 10,000 | 12,836 | Project is complete |
| Highlift Pump Rebuild | 20,077 | 20,077 | 20,077 | This project was added to the capital budget later in the year and approved by Council. |
| WTP Replacement Air Conditioning Unit | 45,487 | 45,487 | - | The unit has been ordered and is awaiting delivery. |
| Decommissioning of Old Water Tower | 400,000 | 400,000 | - | The contract has been signed, and the work is expected to be completed in the spring of 2027. |
| Total | 6,774,764 | 17,551,640 | 1,362,407 | |
| Wastewater | ||||
| Primary/Secondary Gates | - | 253,760 | - | Project is ongoing. |
| Supervisory Control and Data Acquisition (SCADA) | - | 39,824 | 19,466 | The equipment has been installed and is now in service. The project is complete. |
| Pelletizer; Solid Handling Eng. Study | - | 105,215 | 71,744 | Computers are being purchased. Compatibility issues have been identified with the existing alarm system, and staff are working to resolve them. |
| Sewer Hydraulic Capacity Study | - | 175,000 | 309 | The project is ongoing and is currently in the preliminary design stage. The design may be ready for review in the coming weeks. |
| Manhole Replacement at River/Elm St. Intersection | - | 50,000 | - | The study is underway. Data was collected throughout the summer, and the required information is now being provided to the engineers for assessment. |
| Pollution Prevention Control Plan | - | 10,000 | - | The study is underway. Data was collected throughout the summer, and the information is now being provided to the engineers for review and assessment |
| Process Control Narrative and Operational Plan | - | 40,000 | - | The project has not started yet. Work will begin once the SCADA computers have been replaced. |
| Tree Removal and Perimeter Fencing | - | 8,263 | 9,118 | The plant area has been cleaned up, and the area around the perimeter fencing has been cleared and restored. |
|---|---|---|---|---|
| M01 Raw Sewage Pump Rebuild | 70,000 | 78,668 | 73,065 | The equipment is complete and onsite, ready to be installed during the next scheduled pump cycle. |
| CIPP Sanitary Sewer | 210,000 | 210,000 | 70,952 | The project is ongoing at various locations throughout Town, with most of the work completed in August 2026. |
| Headworks Grit System Assessment | 100,000 | 100,000 | 14,444 | The project is currently on hold following issues identified by the Electrical Safety Authority (ESA) in the headworks area. The project scope may need to be reviewed before work proceeds. |
| Turbine Pump Wet End Replacement | 165,000 | 165,000 | - | Quotes are being obtained for the required equipment and parts |
| Tertiary Sand Filter Maintenance | 85,000 | 85,000 | 68,440 | Filter media replacement completed. |
| Raw Sludge Pump Base Replacement | 20,000 | 20,000 | 10,888 | New pump bases and safety guards have been fabricated and installed. |
| Raw Sewage Pumps | 250,000 | 250,000 | - | The project is currently on hold while electrical issues identified in the headworks area are reviewed. The findings may require changes to the project scope before work can continue. |
| UV System Parts | 25,000 | 25,000 | 22,908 | Parts have been ordered. |
| Pelletizer PM (contractor) | 30,000 | 30,000 | - | The required parts have been ordered, and the necessary fabrication work is complete. |
| Total | 955,000 | 1,645,730 | 442,257 | |
| Public Works | ||||
| Beckwith/Lombard Bridge | 734,933 | 734,933 | 61,056 | Project is ongoing and will continue into 2027 |
| ACMP Program Roads | 1,039,526 | 1,164,283 | 747,357 | Project is complete |
| Traffic Controllers & Intersection Improvements: Brockville and Broadview and additional sensors at Cornelia and Elmsley. | 200,000 | 200,000 | - | The project has been awarded, but work has not yet started. The contractor expects the work to be completed by the end of October 2026 |
| Public Works Design Build | 10,458,520 | 10,458,520 | 201,777 | Construction began in the fall of 2026, with occupancy expected before winter 2027. |
| Total | 11,698,046 | 11,822,803 | 1,109,045 | |
| Planning | ||||
| Building Permit Software | 22,500 | 22,500 | 23,812 | Implementation is underway, with the new system scheduled to go live on January 1, 2027. |
| Official Plan Transportation Master Plan | - | 167,913 | 8,118 | The project is ongoing, with an update to be presented to Council in the coming weeks. |
| Total | 22,500 | 190,413 | 31,930 | |
| Corp |
| Maintenance Manager Software (Public Works and Utilities) | 172,000 | 172,000 | 139,615 | The project is underway and is expected to be completed by the end of 2026. |
|---|---|---|---|---|
| Total | 172,000 | 172,000 | 140,648 |