COMMERCIAL NEW CONSTRUCTION: PROJECT GUIDE
<u>Applicant & Design Team:</u> The following general guideline is meant to assist in preparing to file a more complete application, and contains required drawings from the Town Building By-Law. Further requirements may apply to certain projects, pending technical building code plans review by local building official.
Ø <u>Commercial Designer(s)</u>; Prepare <u>Two (2) Full Sets of Complete Building Plans</u> drawn to scale:
<u>Note</u>: Owner and/or Tenant to engage professional design services. Project Designer(s) to complete supporting
documents such as ‘OBC design data Matrix’, ‘Commitment to General Review’ and/or ‘SB-10 Energy Efficiency’;
Ø <u>Site Plan Design</u>; to meet Town Zoning By-Law for planning review: a) On Property Site Plan; All existing structures/stairs, streets, parking stalls, services/utilities (sewer, water/meter, hydro, gas, etc.). <u>Note</u>: <u>Provide copy of any existing Land Survey of record</u>; See local registry office and/or inquire within to search property file records. Add new information to suit proposal, or plot separately in relation to. Required to verify any legal easement/private-right-of way access routes, building position/proximity to lot lines, overhead power lines, etc. <u>Important Note</u>: Any planning pre-approval such as a minor variance, re-zoning or Site Plan Control Agreement is applicable law and must be approved in full for any effective building code plans review time period to commence.
<u>Architectural/Structural Design</u>; to meet Town Building By-Law for Building Code review:
b) <u>Existing Interior Demolition Floor Plans</u> of all levels complete with; Wall Partitions/Room Use, Plumbing, Doors & Windows, Exits/Stairs/Corridors, Mechanical/Utility, Electrical & Fire Detection/Protection/Separation systems; c) <u>Hazardous Materials Report</u> by Environmental agency (older building re-purposed) for asbestos, mold, etc; The Base building/Interior Demo. application, can be filed in advance and obtained separately from a reno permit. d) <u>Existing Building Elevation/Photo</u>; Exterior finishes, light, signs(separate permit); Height of entry floor to grade; e) <u>Proposed Floor Plans</u> of all levels complete with all new changes to; Wall Partitions/Room Use, Plumbing, Doors & Windows, Exits/Stairs/Corridors, Mechanical/Utility, Electrical & Fire Detection/Protection/Separation systems; f) <u>Cross Section Detail</u> of existing/new fire separation rated floor/ceiling, walls, posts/beam and roof assemblies; g) <u>Structural Engineering</u>; Pre-Fabricated Floor, Beam or Roof Truss Layout/Specs.; or as required by Official. h) <u>Electrical Design/Review of Fire Protection System</u> changes, by a Qualified Source: Emergency Exit Lighting/Signs, Smoke Alarm/Heat detector or Fire Alarm Layout, or any other early warning/evacuation systems. Clearly identify any existing early evacuation/detection systems to either remain, be replaced or relocated, etc.; i) <u>Mechanical Design/Review of Heating & Ventilation</u> changes by a Qualified Source: Full HVAC Design documents; Small building HVAC Designer to fill out Schedule 1 form. Engineer’s to complete general review form.
<u>Important Information:</u> 1) Building Systems, 2) Renovation-Expansion and/or 3) Change of Use;
Ø Building Systems; □-Wall Partitions/Fire separations □-Structural/Framing/Floor/Foundation □-Plumbing-
Drains/Vent/Water/Sewer □-Electrical/Smoke Alarms/Emergency Lighting/Exit Sign □-Fire Alarm & Detection
□-HVAC-Heating/Venting/Exhaust □-Sprinkler/Corridor/Stair □-Exterior wall/Thermal/Roofing □-Water/Drainage
<u>Applicant for Permit</u>: File an ‘<u>Application for a Permit to Construct or Demolish’</u> form;
- Declare the Current/Existing Use and the Proposed/New Use on the application;
- Total the Area of Work (Square Feet) by Designer using gross building area;
- Declare an accurate Project Value ($) for all Labour and Materials, Equipment, Overhead and professional related services to complete all work; -Permit Fee by cheque/debit/cash calculated as per Building By-law and verified by staff.
- If application signed by agent (not the owner), owner to sign an authorized agent form. 10/20